7 Watene Road, Mount Wellington, Auckland
Work completed September 2025
- Internal finishes are progressing 
- Exterior cladding is underway 
Work completed August 2025
- Framing and roof complete 
- Windows installed 
- Internal linings and cladding progressing 
Work completed July 2025
- Framing well progressed getting ready for roof 
Work completed June 2025
- Foundation slabs are nearing completion 
- Framing set to commence soon 
Work completed May 2025
- Civil work, drainage and retaining complete 
- Underslab plumbing and foundations underway 
Work completed April 2025
- Demo and earthworks completed 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              