Build Update
7 Watene Road, Mount Wellington, Auckland
Estimated Settlement Date November 2025
Work completed June 2025
Foundation slabs are nearing completion
Framing set to commence soon
Work completed May 2025
Civil work, drainage and retaining complete
Underslab plumbing and foundations underway
Work completed April 2025
Demo and earthworks completed