Work completed September 2025

  • Internal finishes are progressing

  • Exterior cladding is underway


Work completed August 2025

  • Framing and roof complete

  • Windows installed

  • Internal linings and cladding progressing 


Work completed July 2025

  • Framing well progressed getting ready for roof 


Work completed June 2025

  • Foundation slabs are nearing completion

  • Framing set to commence soon


Work completed May 2025

  • Civil work, drainage and retaining complete

  • Underslab plumbing and foundations underway


Work completed April 2025

  • Demo and earthworks completed