Build Update
52 Taramea Street, Avondale


Work completed January 2026

  • External cladding complete

  • Internal and external paint progressing


Work completed December 2025

  • Roofing and windows complete

  • External cladding underway

  • Internal gib commenced


Work completed November 2025

  • Roofing and window installation progressing


Work completed October 2025

  • Framing nearing completion


Work completed September 2025

  • Concrete slabs are complete

  • Framing underway   


Work completed August 2025

  • Civils completed

  • Driveway poured and slabs underway  


Work completed July 2025

  • Demo complete 

  • Earthworks underway