Build Update
83 Ruawai Road, Mount Wellington, Auckland
Work completed August 2025
- Final preparations in progress for October move in 
Work completed July 2025
- Painting and cladding are progressing 
Work completed June 2025
- Roof and windows complete, making homes weathertight 
- Preparations are underway for installing GIB 
Work completed May 2025
- Slabs completed 
- Driveway installed 
- Framing progressing for roofs 
Work completed April 2025
- Civil works, slabs and underground services are progressing 
Work completed March 2025
- Demo and civil work completed 
- Retaining installed 
- Drainage & foundations underway 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              