Build Update
2 Riversdale Road, Avondale, Auckland
Estimated Settlement Date March 2024
Work completed February 2024
Work completed January 2024
- Landscaping, fencing and finishing touches underway 
Work completed December 2023
- Titling kitchens and flooring nearing completion 
- Exterior cladding completed and scaffold removed 
Work completed November 2023
- Internal paint underway 
- External cladding nearing completion 
Work completed October 2023
- Building weather-tight 
- Cladding and GIB underway 
Work completed August/September 2023
- Framing nearing completion 
- Roofing and windows to follow 
Work completed July 2023
- Slabs complete 
- Driveway being poured 
Work completed June 2023
- Earthworks and drainage completed 
- Slab preparation in progress 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              