Build Update
39 Pakuranga Road, Pakuranga, Auckland
Homes completed September 2024
Work completed August 2024
- Council final inspection landscaping and interior clean progressing for Settlement in September 
Work completed July 2024
- Cladding 90% complete 
- Internal fit out 50% complete 
- Kitchen and bathroom installation progressing 
Work completed June 2024
- Roofing and windows complete 
- Internal lining and cladding underway 
Work completed May 2024
- Ground and first-floor framing complete 
- Roofing is in progress and window installations underway 
Work completed April 2024
- Slabs complete 
- Driveway and paths poured 
- Ground and first-floor framing in progress 
Work completed March 2024
- Drainage complete 
- Earthworks and utilities completed 
- Under slab plumbing and foundations underway 
Work completed February 2024
- Demo complete 
- Earthworks in progress 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              