Build Update
42 Millen Avenue, Pakuranga


Work completed January 2026

  • Internal paint and external cladding progressing


Work completed December 2025

  • Roofing and windows complete

  • External cladding underway

  • Internal gib commenced


Work completed November 2025

  • Framing now completed and roof installation commencing 


Work completed October 2025

  • Slabs and driveways are completed

  • Framing now underway


Work completed September 2025

  • Civils completed

  • Slabs underway