Build Update
4 Mead Street, Avondale, Auckland
Homes completed October 2024
Work completed September 2024
- External cladding and painting completed 
- Landscaping fencing and final inspections progressing for project handover in October 
Work completed August 2024
- GIB linings complete 
- External cladding and painting in progress 
- Kitchen and tile installation commenced 
Work completed July 2024
- Framing complete 
- Roof and window installation complete 
- GIB lining commencing 
Work completed June 2024
- Ground and first floor framing complete 
- Prepping for roofing to commence 
Work completed May 2024
- Foundations complete 
- Driveway poured 
- Ground floor framing underway 
Work completed April 2024
- Earthworks complete 
- Drainage and under-slab plumbing underway 
Work completed March 2024
- Demo complete 
- Earthworks ready to commence 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              