Build Update
11 Glenties Lane, Ellerslie


Work completed August 2026

  • Gib installation is nearing completion

  • Decorating now underway


Work completed July 2026

  • Buildings are weathertight

  • Services installation is progressing, ready for Gib


Work completed June 2026

  • Framing is now complete

  • Site now ready for roof installation


Work completed May 2026

  • Framing well progressed

  • Getting ready for roof installation 


Work completed April 2026

  • Plumbing and drainage complete

  • Slabs underway 


Work completed March 2026

  • Demolition complete

  • Earthworks and drainage underway