Build Update
1 Frank Grey Place, Otahuhu, Auckland
Homes completed March 2024
Work completed January 2024
- Exterior cladding completed and scaffold removed 
- Bathrooms and kitchens underway 
- Landscaping and fencing commenced 
Work completed December 2023
- Buildings weathertight 
- Cladding progressing 
- Units lined and stop ready for paint 
Work completed November 2023
- Roofs installed 
- Windows installed 
- Serviced install ready for linings 
Work completed October 2023
- Slabs completed 
- Preparing framing for roofing 
Work completed August/September 2023
- Drainage completed 
- Services installed 
- Slab pour imminent 
Work completed July 2023
- Demo complete 
- Earthworks in progress 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              