Build Update
191 England Street, Linwood, Christchurch
Completed January 2023
Work completed November/December 2022
- Cladding finished around entry doors 
- Plumbers 95% complete 
- Electrical 95% complete 
- Range hoods installed 
- Carpet layers finishing of stairs 
Work completed October 2022
- Painters have all bathroom and kitchens ready 
- Kitchens are being installed 
- Builders still working on cladding 
- Installed all iron cladding last week/ waiting on flashings to finish 
- Tilers started 
Work completed September 2022
- Doors currently getting installed 
- Brick layers up half way 
- Cavity battens on for pre clad inspection 
- Gib fixers are 85% complete 
- Gib stops have made a start on units 1,2,3,4 and waiting on inspection for 5-8 to proceed 
- Pushing to have painter done and out by 25th 
Work completed August 2022
- Civil works complete 
- Framing complete 
- Roof complete 
- Close-in commenced 
Work completed July 2022
- Foundations complete 
- Civil works and services complete 
- Framing commenced 
 
                         
               
               
               
               
               
               
               
               
              