Build Update
12 Edward Avenue, Edgeware, Christchurch
Homes completed April 2023
Work completed March 2023
- Concrete paths and patios booked to pour on the 11th 
- Plumbers fit off completed 
- Builder fit off completed 
- Electrical fit off almost complete 
- Retaining wall complete 
- Currently working on fencing 60% complete 
Work completed February 2023
- Cladding 98% complete 
- Kitchen install started 
- Painters finished 5 units 
- Exterior paid due to completed in weeks time 
Work completed January 2023
- Gib stopper have started 
- Brick layers started 
- Weathertex started going up 
Work completed November/December 2022
- Plumbers on-site doing pre pipe 
- Sparkys on-site doing pre wire 
- Builders straighting and installing ceiling battens and blocking 
- Pre line inspection booked for 20th 
Work completed October 2022
- Drive way about to be poured 
- Roof install this week on back units 
- Currently wrapping the buildings 
- Facia and gutter installed 
Work completed September 2022
- First floor frames stood and currently bracing them up 
- Trusses turned up on site 
- Driveway to carry on construction early next month 
Work completed August 2022
- Foundations complete 
- Inground services complete 
- Framing commenced 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              