Build Update
33 Convoy Lane, Otahuhu, Auckland
Homes completed March 2025
Work completed February 2025
- Cladding complete 
- Interior fit-out and landscaping in progress 
Work completed January 2025
- Roof & windows installed 
- GIB installed 
- Cladding progressing 
Work completed December 2024
- Ground and first floor framing complete 
- Roof and window installation nearing completion 
Work completed November 2024
- Foundations complete 
- Framing progressing for roof 
Work completed October 2024
- Demolition, civils, retaining and drainage completed 
- Slabs underway 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              