Build Update
34 Briarley Street, Tauranga


Work completed February 2026

  • Roofs on

  • Windows arriving onsite soon

  • Cladding and internal works to begin the end of this month 


Work completed January 2026

  • Ground and first floor framing up

  • Trusses arrive on site for installation


Work completed December 2025

  • External fencing has been installed 

  • Slabs were poured on the last working day of the year

  • Frames to arrive onsite on January


Work completed November 2025

  • Demo and earthworks complete

  • Foundation areas are being boxed out in preparation for the concrete pour