Build Update
54 Barrack Road, Mount Wellington, Auckland
Work completed September 2024
- Scaffolding down 
- External cladding and painting completed 
- GIB lining completed with painting and interior fit outs in progress 
- Landscaping work commenced 
Work completed August 2024
- Homes weathertight with roofs and windows complete 
- GIB internal linings underway 
- External cladding and painting progressing 
Work completed July 2024
- Framing completed 
- Roof and window install commencing 
Work completed June 2024
- Ground floor framing complete 
- First floor framing in progress 
Work completed May 2024
- Retaining and draining complete 
- Foundations complete 
Work completed April 2024
- Earthworks complete 
- Retaining and draining underway 
Work completed March 2024
- Demo complete 
- Earthworks ready to commence 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              