Work completed June 2026

  • Slabs and driveways are complete

  • Framing has commenced


Work completed May 2026

  • Earthworks and retaining completed

  • Drainage nearing completion, ready to commence foundations 


Work completed April 2026

  • Earthworks in process


Work completed March 2026

  • Demolition completed for earthworks and retaining to commence