Build Update
48 Torrington Crescent, Glen Innes, Auckland
Work completed April 2025
- Code compliance achieved, ready for owners to move in 
- Landscaping and fencing finalising 
Work completed March 2025
- Internal finishes progressing 
- Cladding complete 
- Landscaping underway 
Work completed February 2025
- Stop and paint progressing to interiors 
- Cladding progressing 
Work completed January 2025
- Roofing and windows installed 
- Services and insulation installed ready for GIB 
Work completed December 2024
- Ground and first floor framing complete 
- Driveway complete 
- Preparing for roofing and window installation 
Work completed November 2024
- Foundations complete 
- Framing progressing for roof 
- Driveway forming underway 
Work completed October 2024
- Demolition, civils, retaining and drainage completed 
- Slabs underway 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              