Build Update
Seaside Peninsula, 127 Luke Street East

Estimated Settlement Date November 2023


Work completed August/September 2023

  • Kitchens, Bathrooms and flooring are progressing

  • Fencing and landscape underway


Work completed July 2023

  • Full framing and cavity pass and 90% of the cladding installed

  • Exterior paint is underway

  • Gib is on-site to start internal linings


Work completed June 2023

  • Roof install in progress

  • Window installation commencing second week of July


Work completed May 2023

  • 1st story frames on site and being stood

  • On track for trusses and roof work


Work completed April 2023

  • Earthworks drainage and under slab plumbing have been completed for slab installation to progress