Build Update
31 Convoy Lane, Otahuhu, Auckland
Work completed August 2025
- Internal fit out and landscaping progressing 
Work completed June 2025
- Roofs complete 
- Project is weathertight getting ready for internal linings and cladding 
Work completed June 2025
- Framing for both the ground and first floors now complete 
- Preparations underway for the roof installation 
Work completed May 2025
- Slabs and driveways now complete and ready for frames 
Work completed April 2025
- Demo and earthworks completed 
 
                         
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
               
              